Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Megha | 20055921 | Babuwapur & Shahpur Water Supply scheme | 389.15 | 145.38 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 16781.00 | 13867.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Triveniganj | Babuwapur | 436053 | Babuwapur | 219 | 218 | 100 | Work In Progress | Not Certified |
| 2 | Barabanki | Triveniganj | Shahpur | 436054 | Shahpur | 221 | 220 | 100 | Work In Progress | Not Certified |
| 3 | Barabanki | Triveniganj | Shahpur | 436055 | Dehwa | 101 | 100 | 99 | Work In Progress | Not Certified |
| 4 | Barabanki | Triveniganj | Bahadurpur | 436062 | Kazipur | 67 | 61 | 91 | Work In Progress | Not Certified |
| 5 | Barabanki | Triveniganj | Babuwapur | 436112 | Ganesh Pur | 72 | 72 | 100 | Har Gar Jal | Not Certified |