Scheme Details
DISTRICT
Jaunpur
AGENCY
AFCONS
SCHEME ID
20056103
SCHEME NAME
RASULPUR GRAM PANCHAYAT WATER SUPPLY SCHEME
ESTIMATED COST
277.21
EXPENDITURE
110.43
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
16
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12307.00
Meter
Length Laid
10578.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Machhlishahr | Rasulpur | 469578 | Rasulpur | 283 | 283 | 100% | Har Ghar Jal | Not Certified |
| 2 | Jaunpur | Machhlishahr | Rasulpur | 469579 | Marufpur | 160 | 148 | 92% | Work In Progress | Not Certified |