Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Indian Hume Pipe | 20056125 | Nandgaon PWS | 200.37 | 154.11 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 15 | 15 | Yes | 0 | NA | No | 10027.00 | 10396.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Auraiya | Auraiya | Nandgaon | 420887 | Nandgaon | 117 | 117 | 100 | Har Gar Jal | Certified |
| 2 | Auraiya | Auraiya | Nandgaon | 420888 | Parsottampur | 43 | 43 | 100 | Har Gar Jal | Certified |
| 3 | Auraiya | Auraiya | Nandgaon | 420889 | Marnai | 80 | 80 | 100 | Har Gar Jal | Certified |