Scheme Details
DISTRICT
Ambedkar Nagar
AGENCY
Vindhya-GAJA (JV)
SCHEME ID
20056336
SCHEME NAME
POORA DARBAR WSS
ESTIMATED COST
666.05
EXPENDITURE
560.18
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
7
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
33291.00
Meter
Length Laid
45219.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
7 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ambedkar Nagar | Bhiti | Dahema | 438691 | Dahema | 208 | 189 | 91% | Work In Progress | Not Certified |
| 2 | Ambedkar Nagar | Bhiti | KICHUTE | 438692 | KICHHUTI | 124 | 124 | 100% | Har Ghar Jal | Not Certified |
| 3 | Ambedkar Nagar | Bhiti | KICHUTE | 438693 | KURRA | 132 | 132 | 100% | Har Ghar Jal | Not Certified |
| 4 | Ambedkar Nagar | Bhiti | Poora Darbar | 438694 | Poora Darbar | 228 | 206 | 90% | Work In Progress | Not Certified |
| 5 | Ambedkar Nagar | Bhiti | Poora Darbar | 438695 | Dupatti | 97 | 75 | 77% | Work In Progress | Not Certified |
| 6 | Ambedkar Nagar | Bhiti | Mallepur | 438699 | Mallepur | 191 | 182 | 95% | Work In Progress | Not Certified |
| 7 | Ambedkar Nagar | Bhiti | Mallepur | 438700 | Saraiya | 43 | 43 | 100% | Har Ghar Jal | Not Certified |