Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Shamli
AGENCY Gayatri Projects LTD
SCHEME ID 20056381
SCHEME NAME Bahavari Village Water Supply Scheme Reorganisation
ESTIMATED COST 472.68
EXPENDITURE 356.78
AUTOMATION STATUS
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 53
Procured 53 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 13.81 Meter
Length Laid 13500.00 Meter

Scheme Assigned Villages

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Shamli Shamli Bahavari 384913 Bahavari 1182 1182 100% Har Ghar Jal Not Certified