Scheme Details
DISTRICT
Shravasti
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20056547
SCHEME NAME
EKAUNA DEHAT RO SV PWS
ESTIMATED COST
761.16
EXPENDITURE
338.54
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
0
Work Started
0
Work Completed
0
Solar Plant
Required
0
Procured
0
KW
Work Status
NA
Electric
Required
28
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
45221.00
Meter
Length Laid
44500.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shravasti | Ekona | Ekauna Dehat | 443440 | Ekauna | 1739 | 1735 | 100% | Work In Progress | Not Certified |