Scheme Details
DISTRICT Barabanki
AGENCY Vindhya-GAJA (JV)
SCHEME ID 20056640
SCHEME NAME Baina tikaihar & Pilhati Haidrabad Water Supply Scheme
ESTIMATED COST 694.78
EXPENDITURE 337.48
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 2
Boring Done 2
Air Compressor Done 2
O.P. Unit Done 2
OHT Progress
Required 1
Work Started 0
Work Completed 1
Solar Plant
Required 42
Procured 42 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 38106.00 Meter
Length Laid 38106.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Nindaura Baina Tikaihar 434419 Baina Tikaihar 503 501 100% Work In Progress Not Certified
2 Barabanki Nindaura Pilehati Haidrabad 434424 Pilehati Haidrabad 195 189 97% Work In Progress Not Certified
3 Barabanki Nindaura Pilehati Haidrabad 434425 Alinagar Karaund 180 176 98% Work In Progress Not Certified
4 Barabanki Nindaura Pilehati Haidrabad 434446 KODHAWA 159 155 97% Work In Progress Not Certified