Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | AFCONS | 20056968 | JARASI GRAM PANCHAYAT WATER SUPPLY SCHEME | 430.28 | 184.87 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 27 | 0 | NA | 0 | NA | No | 24908.00 | 22000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Jaunpur | Dobhi | Jarasi | 471341 | Loharakhor | 150 | 146 | 97 | Work In Progress | Not Certified | 
| 2 | Jaunpur | Dobhi | Jarasi | 471342 | Jarasi | 407 | 398 | 98 | Work In Progress | Not Certified | 