Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20056976 | BADAULI (GOGP) JJM | 588.35 | 322.06 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 44 | 44 | Yes | 0 | NA | No | 26815.00 | 26815.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Ahirohi | Gopalpur | 413055 | Gopalpur | 209 | 172 | 82 | Work In Progress | Not Certified |
| 2 | Hardoi | Ahirohi | Saripur Bramhnan | 413056 | Saripur Bramhnan | 241 | 240 | 100 | Work In Progress | Not Certified |
| 3 | Hardoi | Ahirohi | Dighiya | 413063 | Dighiya | 306 | 303 | 99 | Work In Progress | Not Certified |
| 4 | Hardoi | Ahirohi | Badauli | 413079 | Badauli | 553 | 540 | 98 | Work In Progress | Not Certified |