Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20057084
SCHEME NAME
JIGNIYA KALAN (GOGP) JJM
ESTIMATED COST
542.17
EXPENDITURE
372.03
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
42
Procured
42
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17457.00
Meter
Length Laid
15170.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | TADIYAWAN | JIGNIYA KHURD | 412870 | JIGINIYA KHURD | 260 | 260 | 100% | Har Ghar Jal | Not Certified |
| 2 | Hardoi | TADIYAWAN | JIGINIYA KALA | 412871 | JIGNIYA KALAN | 180 | 180 | 100% | Har Ghar Jal | Not Certified |
| 3 | Hardoi | TADIYAWAN | RAWAL | 412907 | RAWAL | 340 | 340 | 100% | Har Ghar Jal | Not Certified |