Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20057275 | PUNNIYA (GOGP) jjm | 559.98 | 301.93 | view more |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 44 | 44 | Yes | 0 | NA | No | 23058.00 | 23058.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Ahirohi | Karahi | 413034 | Karahi | 263 | 220 | 84 | Work In Progress | Not Certified |
| 2 | Hardoi | Ahirohi | Karahi | 413035 | Daudpur | 215 | 214 | 100 | Work In Progress | Not Certified |
| 3 | Hardoi | Ahirohi | Punniya | 413075 | Punniya | 431 | 430 | 100 | Work In Progress | Not Certified |