Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20057384
SCHEME NAME Kundeli water supply scheme
ESTIMATED COST 301.15
EXPENDITURE 194.60
AUTOMATION STATUS
SCHEME STATUS Operation & Maintenance
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 23
Procured 23 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 8546.00 Meter
Length Laid 8546.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Jagat Kundeli 401951 Kundeli 286 284 99% Work In Progress Not Certified
2 Budaun Jagat Kundeli 401952 Phulaincha 52 50 96% Work In Progress Not Certified
3 Budaun Jagat Kundeli 401953 Isapur 166 165 99% Work In Progress Not Certified
4 Budaun Jagat Kundeli 401954 Karela 23 22 96% Work In Progress Not Certified