Scheme Details
DISTRICT
Budaun
AGENCY
PNC-SPML-JV
SCHEME ID
20057415
SCHEME NAME
Naum tikanna pukhta water supply scheme
ESTIMATED COST
291.58
EXPENDITURE
113.77
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
8960.00
Meter
Length Laid
8960.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Budaun | Dataganj | Naum Tikanna Pukhta | 402301 | Naum Tikanna Pukhta | 536 | 534 | 100% | Work In Progress | Not Certified |