Scheme Details
DISTRICT Budaun
AGENCY PNC-SPML-JV
SCHEME ID 20057459
SCHEME NAME Jagtua water supply scheme
ESTIMATED COST 280.44
EXPENDITURE 133.18
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7588.00 Meter
Length Laid 7588.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Budaun Islamnagar Jagtua 401214 Jagtua 155 155 100% Har Ghar Jal Not Certified
2 Budaun Islamnagar Jagtua 401215 Saraya 136 136 100% Har Ghar Jal Not Certified
3 Budaun Islamnagar Jagtua 401216 Saidsarai 202 202 100% Har Ghar Jal Not Certified