Scheme Details
DISTRICT Bareilly
AGENCY NCC Ltd.
SCHEME ID 20057546
SCHEME NAME Chandowa
ESTIMATED COST 237.83
EXPENDITURE 94.25
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 0
O.P. Unit Done 0
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 14
Procured 14 KW
Work Status No
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 7511.00 Meter
Length Laid 7400.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Bareilly Aalampur Jafrabad Chandowa 403633 Chandowa 236 236 100% Har Ghar Jal Not Certified
2 Bareilly Aalampur Jafrabad Chandowa 403634 Fatehepur Saratu 121 121 100% Har Ghar Jal Not Certified