DISTRICT Hardoi
AGENCY NCC Ltd.
SCHEME ID 20057686
SCHEME NAME BURHANPUR (GOGP) JJM
ESTIMATED COST 356.08
EXPENDITURE 278.49
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 4
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 25
Procured 25 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 10491.00 Meter
Length Laid 9566.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

4 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Hardoi TODARPUR BURHANPUR 412028 BURHANPUR 278 278 100% Har Ghar Jal Not Certified
2 Hardoi TODARPUR BURHANPUR 412029 BARELA 144 144 100% Har Ghar Jal Certified
3 Hardoi TODARPUR HATHIPUR SARAY 412055 HATHIPUR 200 200 100% Har Ghar Jal Not Certified
4 Hardoi TODARPUR HATHIPUR SARAY 412056 SARAI PAINGU 100 100 100% Har Ghar Jal Not Certified