Scheme Details
DISTRICT
Barabanki
AGENCY
VSA
SCHEME ID
20057789
SCHEME NAME
Bindaura Paraspur Water Supply Scheme
ESTIMATED COST
244.93
EXPENDITURE
156.40
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
16
Procured
16
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
11700.00
Meter
Length Laid
11700.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Ramnagar | Bindaura Paraspur | 434922 | Bindaura Paraspur | 223 | 219 | 98% | Work In Progress | Not Certified |
| 2 | Barabanki | Ramnagar | Bindaura Paraspur | 434923 | Puraina | 191 | 191 | 100% | Har Ghar Jal | Certified |