Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20057804 | JUGRAJPUR (GOGP) JJM | 403.83 | 266.00 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 16635.00 | 16635.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | KOTHAWAN | JUGRAJPUR | 413312 | JUGRAJPUR | 165 | 165 | 100 | Har Gar Jal | Not Certified |
| 2 | Hardoi | KOTHAWAN | JUGRAJPUR | 413313 | GATHIYA | 147 | 147 | 100 | Har Gar Jal | Not Certified |
| 3 | Hardoi | KOTHAWAN | RAYPUR SOMVANSHI | 413352 | RAYPUR SOMVANSHI | 178 | 178 | 100 | Har Gar Jal | Not Certified |
| 4 | Hardoi | KOTHAWAN | RAYPUR SOMVANSHI | 413353 | SHANKARPUR | 173 | 172 | 99 | Work In Progress | Not Certified |
| 5 | Hardoi | KOTHAWAN | RAYPUR SOMVANSHI | 413354 | JAITAPUR | 54 | 54 | 100 | Har Gar Jal | Not Certified |