Scheme Details
DISTRICT Azamgarh
AGENCY LC INFRA
SCHEME ID 20057806
SCHEME NAME Khaniyara WATER Supply scheme
ESTIMATED COST 342.89
EXPENDITURE 198.79
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 18124.00 Meter
Length Laid 9249.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Azamgarh Lalganj Khaniyara 464371 Manauwa 37 35 95% Work In Progress Not Certified
2 Azamgarh Lalganj Khaniyara 464372 Kurebhar 69 67 97% Work In Progress Not Certified
3 Azamgarh Lalganj Khaniyara 464373 Khaniyara 655 653 100% Work In Progress Not Certified