Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20057814 | BAJPUR NAKTAURA (GOGP) JJM | 564.13 | 347.28 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 42 | 42 | Yes | 0 | NA | No | 23915.00 | 21436.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | BAWAN | BAJPUR NAKTAURA | 412411 | BAJPUR NAKTAURA | 664 | 664 | 100 | Har Gar Jal | Certified |
| 2 | Hardoi | BAWAN | MATTIPUR | 412412 | MATTIPUR | 240 | 240 | 100 | Har Gar Jal | Not Certified |
| 3 | Hardoi | BAWAN | DULARPUR TIGANWA | 412465 | DULARPUR | 418 | 418 | 100 | Har Gar Jal | Not Certified |
| 4 | Hardoi | BAWAN | DULARPUR TIGANWA | 412466 | MAHIMAPUR | 1 | 1 | 100 | Har Gar Jal | Not Certified |