Scheme Details

S.No. District Name Agency Name Scheme Id Scheme Name Estimated Cost Expenditure Automation Integration Status
1 Basti Megha 20057865 SEMARA GP wss 145.05 49.88 Not Integrated

Scheme Physical Progress

Village Covered T/W OHT Solar Plant Electric Distribution (Line Laying in meter.)
Required Boring Done Air Compressor done O. P. Unit done Required Work Started Work Completed Required Procured (KW) Work status Required Transformer Procured Work status Total Length Length Laid
4 1 1 1 1 1 1 1 13 13 Yes 0 NA No 7019.00 7019.00

Scheme Assigned Villages

Sno. District Name Bolck Panchayat Village ID Village Name House Holds FHTC FHTC % Har Gar Jal Certified
1 Basti Dubaulia SEMARA 450175 Samera 86 85 99 Work In Progress Not Certified
2 Basti Dubaulia SEMARA 450180 Pipra Brijlal 40 40 100 Har Gar Jal Not Certified
3 Basti Dubaulia SEMARA 450181 Dariyauna 60 60 100 Har Gar Jal Not Certified
4 Basti Dubaulia SEMARA 450182 Babhanpura Ghanshyamjot 45 45 100 Har Gar Jal Not Certified