Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Barabanki | VSA | 20057870 | Mallapur Arsanda & Rampur Khargi Water Supply Scheme | 499.75 | 226.52 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 30 | Yes | 0 | NA | No | 26062.00 | 23210.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Barabanki | Ramnagar | Malpur Arsanda | 435005 | Malpur Arsanda | 222 | 219 | 99 | Work In Progress | Not Certified | 
| 2 | Barabanki | Ramnagar | Malpur Arsanda | 435006 | Bazidpur | 100 | 97 | 97 | Work In Progress | Not Certified | 
| 3 | Barabanki | Ramnagar | RAMPUR KHARGI | 435013 | PURE KINHAULI | 125 | 122 | 98 | Work In Progress | Not Certified | 
| 4 | Barabanki | Ramnagar | RAMPUR KHARGI | 435014 | SURWARI | 110 | 108 | 98 | Work In Progress | Not Certified | 
| 5 | Barabanki | Ramnagar | RAMPUR KHARGI | 435015 | RAMPUR KHARGI | 231 | 228 | 99 | Work In Progress | Not Certified |