DISTRICT
Bareilly
AGENCY
NCC Ltd.
SCHEME ID
20057887
SCHEME NAME
Dauli Raghuveer Dayal
ESTIMATED COST
450.12
EXPENDITURE
255.77
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
16028.00
Meter
Length Laid
16000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bareilly | Kyara | Dauli Raghuber Dayal | 403323 | Dauli Raghuber Dayal | 1227 | 1227 | 100% | Har Ghar Jal | Not Certified |