Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Hardoi | NCC Ltd. | 20057894 | ASALAPUR (GOGP) JJM | 673.97 | 356.56 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 49 | 49 | Yes | 0 | NA | No | 32091.00 | 32091.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Shahabad | ASLAPUR | 411822 | ASLAPUR | 247 | 243 | 98 | Work In Progress | Not Certified | 
| 2 | Hardoi | Shahabad | ASLAPUR | 411823 | NAGAMAU | 83 | 83 | 100 | Har Gar Jal | Not Certified | 
| 3 | Hardoi | Shahabad | BOOTAMAU BAKAURA | 411901 | BOOTAMAU | 295 | 293 | 99 | Work In Progress | Not Certified | 
| 4 | Hardoi | Shahabad | BOOTAMAU BAKAURA | 411902 | BAKAURA | 150 | 148 | 99 | Work In Progress | Not Certified | 
| 5 | Hardoi | Shahabad | SAKRAULI | 411931 | Sakrauli | 407 | 404 | 99 | Work In Progress | Not Certified | 
| 6 | Hardoi | Shahabad | SAKRAULI | 411932 | Fadnapur | 124 | 122 | 98 | Work In Progress | Not Certified |