Follow us on for latest updates.    |    To Lodge Complaint Call On 18001212164   or   visit   www.jalsamadhan.in


Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Moradabad
AGENCY NKG-PRIMUS (JV)
SCHEME ID 20058134
SCHEME NAME Narsara & Banither Village Water Supply Scheme.
ESTIMATED COST 343.53
EXPENDITURE 104.34
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 6
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 20
Procured 20 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 15015.00 Meter
Length Laid 15000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

6 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Moradabad Bilari NARSARA 388516 NARSARA 145 144 99% Work In Progress Not Certified
2 Moradabad Bilari NARSARA 388517 NASEERPUR DHANNA 73 66 90% Work In Progress Not Certified
3 Moradabad Bilari BANIATHER 388546 Baniather 211 202 96% Work In Progress Not Certified
4 Moradabad Bilari BANIATHER 388547 Allapur Urf Rampur 108 100 93% Work In Progress Not Certified
5 Moradabad Bilari BANIATHER 388549 Fatehpur Chandan 1 1 100% Har Ghar Jal Not Certified
6 Moradabad Bilari BANIATHER 677746 RAMPUR PATTI MUKTAL 3 1 33% Work In Progress Not Certified