Scheme Details
DISTRICT
Bulandshahr
AGENCY
JMC - Lakshmi (JV)
SCHEME ID
20058178
SCHEME NAME
Pali anandgarhi & Sabdalpur WSS
ESTIMATED COST
447.70
EXPENDITURE
300.16
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
17180.00
Meter
Length Laid
14000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bulandshahr | Unchagaon | Sabdalpur | 393546 | Sabdalpur | 187 | 187 | 100% | Har Ghar Jal | Not Certified |
| 2 | Bulandshahr | Unchagaon | Pali Anandgarhi | 393562 | Pali Anandgarhi | 647 | 632 | 98% | Work In Progress | Not Certified |