Scheme Details
DISTRICT
Ghazipur
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20058354
SCHEME NAME
Deorhi W/S SCHEME
ESTIMATED COST
304.60
EXPENDITURE
125.74
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
25
Procured
25
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
12609.00
Meter
Length Laid
8857.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ghazipur | Zamania | Deorhi | 473890 | Deorhi | 375 | 375 | 100% | Har Ghar Jal | Not Certified |
| 2 | Ghazipur | Zamania | Deorhi | 473891 | Kabirpur T. Gaighat | 40 | 39 | 98% | Work In Progress | Not Certified |
| 3 | Ghazipur | Zamania | Deorhi | 473892 | Parnehapur Urf Bahadurpur | 39 | 36 | 92% | Work In Progress | Not Certified |