Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Power Mech Projects Ltd | 20058441 | Maharajpur&Kasipur Mohan Gram Panchayat Water Supply Scheme | 363.98 | 214.44 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 27 | 27 | Yes | 0 | NA | No | 17303.00 | 17303.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Pratapgarh | Kunda | KASHIPUR MOHAN | 429412 | EBRAHIMPUR | 65 | 64 | 98 | Work In Progress | Not Certified |
| 2 | Pratapgarh | Kunda | KASHIPUR MOHAN | 429413 | Kashipur Mohan | 226 | 225 | 100 | Work In Progress | Not Certified |
| 3 | Pratapgarh | Kunda | Mahrajpur | 429438 | Mahrajpur | 208 | 208 | 100 | Har Gar Jal | Not Certified |
| 4 | Pratapgarh | Kunda | Mahrajpur | 429439 | Harishanker | 112 | 111 | 99 | Work In Progress | Not Certified |
| 5 | Pratapgarh | Kunda | Mahrajpur | 429440 | Kalyanpur | 60 | 44 | 73 | Work In Progress | Not Certified |
| 6 | Pratapgarh | Vihar | Mahrajpur | 429510 | Mahrajpur | 219 | 204 | 93 | Work In Progress | Not Certified |