Scheme Details
DISTRICT
Ayodhya
AGENCY
UNIVERSAL MEP
SCHEME ID
20058513
SCHEME NAME
Neora WSS
ESTIMATED COST
551.79
EXPENDITURE
480.12
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
1
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
37
Procured
37
KW
Work Status
No
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
20242.00
Meter
Length Laid
20242.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
1 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Mavai | Neora | 436233 | Neora | 947 | 912 | 96% | Work In Progress | Not Certified |