Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Mau
AGENCY LC INFRA
SCHEME ID 20058542
SCHEME NAME RO Ibrahima Bad First Village Water Supply Scheme
ESTIMATED COST 224.46
EXPENDITURE 100.36
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 2
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 0
Work Completed 0
Solar Plant
Required 14
Procured 0 KW
Work Status NA
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 14081.00 Meter
Length Laid 13000.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

2 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Mau Dohri Ghat Ibrahima Bad First 464859 Ibrahima Bad 227 226 100% Work In Progress Not Certified
2 Mau Dohri Ghat Ibrahima Bad First 464860 Kharkauli 150 148 99% Work In Progress Not Certified