Scheme Details
DISTRICT
Mau
AGENCY
LC INFRA
SCHEME ID
20058542
SCHEME NAME
RO Ibrahima Bad First Village Water Supply Scheme
ESTIMATED COST
224.46
EXPENDITURE
100.36
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
2
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
0
Work Completed
0
Solar Plant
Required
14
Procured
0
KW
Work Status
NA
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14081.00
Meter
Length Laid
13000.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
2 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Mau | Dohri Ghat | Ibrahima Bad First | 464859 | Ibrahima Bad | 227 | 226 | 100% | Work In Progress | Not Certified |
| 2 | Mau | Dohri Ghat | Ibrahima Bad First | 464860 | Kharkauli | 150 | 148 | 99% | Work In Progress | Not Certified |