Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20058545
SCHEME NAME
BAHADUR NAGAR GOGP JJM
ESTIMATED COST
604.04
EXPENDITURE
427.14
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
42
Procured
42
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23751.00
Meter
Length Laid
23751.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Pihani | Bahadur Nagar | 412134 | Bahadur Nagar | 80 | 80 | 100% | Har Ghar Jal | Certified |
| 2 | Hardoi | Pihani | Bahadur Nagar | 412135 | LOHAR KHEDA | 30 | 30 | 100% | Har Ghar Jal | Certified |
| 3 | Hardoi | Pihani | HINDU NAGAR | 412165 | HINDU NAGAR | 230 | 230 | 100% | Har Ghar Jal | Not Certified |
| 4 | Hardoi | Pihani | HINDU NAGAR | 412166 | KULHAWAR | 120 | 120 | 100% | Har Ghar Jal | Not Certified |
| 5 | Hardoi | Pihani | Rajuapur | 412179 | Rajuapur | 404 | 404 | 100% | Har Ghar Jal | Not Certified |