Scheme Details
DISTRICT Hardoi
AGENCY NCC Ltd.
SCHEME ID 20058576
SCHEME NAME UCHAUL JJM
ESTIMATED COST 253.73
EXPENDITURE 156.05
AUTOMATION STATUS Not Integrated
SCHEME STATUS Trial Run
Scheme Physical Progress
Village Coverage
Village Covered 1
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 1
Solar Plant
Required 18
Procured 18 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 9642.00 Meter
Length Laid 9642.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

1 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Hardoi Pihani UCHAWAL TIGAWAN 412076 UCHAWAL TIGAWAN 246 246 100% Har Ghar Jal Certified