Scheme Details
DISTRICT Barabanki
AGENCY VSA
SCHEME ID 20058594
SCHEME NAME Bhairampur & Basantpur Manjhara Water Supply Scheme
ESTIMATED COST 466.09
EXPENDITURE 236.66
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 37
Procured 37 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 24930.00 Meter
Length Laid 24215.00 Meter

Scheme Assigned Villages

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Barabanki Suratganj Basantpur Manjhara 434745 Basantpur Manjhara 231 228 99% Work In Progress Not Certified
2 Barabanki Suratganj Basantpur Manjhara 434746 Ibrahempurmanjhara 80 77 96% Work In Progress Not Certified
3 Barabanki Suratganj Bhairampur 434886 Bhairampur 507 503 99% Work In Progress Not Certified