Scheme Details
DISTRICT
Prayagraj
AGENCY
Larsen & Toubro Ltd
SCHEME ID
20058687
SCHEME NAME
Deva, Jagua Saraypeetha and Vikrampur Multi Village Water Supply Scheme
ESTIMATED COST
406.05
EXPENDITURE
212.64
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
28662.93
Meter
Length Laid
28660.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Prayagraj | Dhanoopur | Vikrampur | 433336 | Vikram Pur | 181 | 176 | 97% | Work In Progress | Not Certified |
| 2 | Prayagraj | Dhanoopur | Deva | 433367 | Deva | 334 | 306 | 92% | Work In Progress | Not Certified |
| 3 | Prayagraj | Dhanoopur | Jagua Saraypeetha | 433369 | Loka Pur | 27 | 21 | 78% | Work In Progress | Not Certified |
| 4 | Prayagraj | Dhanoopur | Sarai Pitha | 433443 | Sarai Pitha | 476 | 455 | 96% | Work In Progress | Not Certified |