Scheme Details
DISTRICT
Basti
AGENCY
VSA
SCHEME ID
20058711
SCHEME NAME
BEDIPUR & RAGHAWAPUR GP wss
ESTIMATED COST
394.71
EXPENDITURE
277.44
AUTOMATION STATUS
Disconnected
View Live Screen
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
6
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
30
Procured
30
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
18136.00
Meter
Length Laid
18136.00
Meter
Scheme Assigned Villages
6 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Paras Rampur | Raghawapur | 449086 | Raghawapur | 62 | 61 | 98% | Work In Progress | Not Certified |
| 2 | Basti | Paras Rampur | Raghawapur | 449087 | Bop | 75 | 74 | 99% | Work In Progress | Not Certified |
| 3 | Basti | Paras Rampur | Raghawapur | 449088 | Chanda Chaube | 18 | 17 | 94% | Work In Progress | Not Certified |
| 4 | Basti | Paras Rampur | Raghawapur | 449089 | Parashrampur | 27 | 26 | 96% | Work In Progress | Not Certified |
| 5 | Basti | Paras Rampur | Bedipur | 449138 | Bedipur | 271 | 270 | 100% | Work In Progress | Not Certified |
| 6 | Basti | Paras Rampur | Raghawapur | 696665 | RAGHAWAPUR | 53 | 53 | 100% | Har Ghar Jal | Not Certified |