Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20058738 | Bedar bakthpur Jado Water Supply Scheme | 311.44 | 202.97 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 30 | 31 | Yes | 0 | NA | No | 7160.00 | 6764.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Kotwali | Bedar Bakhtpur Jado | 386397 | Bedar Bakhtpur Jado | 333 | 330 | 99 | Work In Progress | Not Certified |
| 2 | Bijnor | Kotwali | Bedar Bakhtpur Jado | 386398 | Chamru Nawada | 175 | 173 | 99 | Work In Progress | Not Certified |
| 3 | Bijnor | Kotwali | Bedar Bakhtpur Jado | 386399 | Shah Alipur Jaman | 174 | 174 | 100 | Har Gar Jal | Not Certified |