Scheme Details
DISTRICT
Shahjahanpur
AGENCY
NCC Ltd.
SCHEME ID
20058745
SCHEME NAME
ABDALPUR ALBELA & KATKA WSS
ESTIMATED COST
314.49
EXPENDITURE
211.71
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
1
Solar Plant
Required
20
Procured
20
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
14450.00
Meter
Length Laid
14450.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Shahjahanpur | Jalalabad | Abdalpur Albela | 407697 | Abdadpur Albela | 155 | 155 | 100% | Har Ghar Jal | Not Certified |
| 2 | Shahjahanpur | Jalalabad | Katka | 407698 | Katka | 137 | 137 | 100% | Har Ghar Jal | Not Certified |
| 3 | Shahjahanpur | Jalalabad | Katka | 407699 | Katkiya | 131 | 131 | 100% | Har Ghar Jal | Not Certified |
| 4 | Shahjahanpur | Jalalabad | Abdalpur Albela | 407700 | Jauhana | 86 | 86 | 100% | Har Ghar Jal | Not Certified |