Scheme Details
DISTRICT
Hardoi
AGENCY
NCC Ltd.
SCHEME ID
20058778
SCHEME NAME
SHAHPUR NAU GOGP JJM
ESTIMATED COST
541.49
EXPENDITURE
343.98
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
5
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
35
Procured
35
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
23506.00
Meter
Length Laid
23506.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
5 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Hardoi | Shahabad | VIHGAWAN | 411900 | VIHGAWAN | 242 | 226 | 93% | Work In Progress | Not Certified |
| 2 | Hardoi | Shahabad | Raipur | 411921 | Gulraha | 102 | 102 | 100% | Har Ghar Jal | Not Certified |
| 3 | Hardoi | Shahabad | Raipur | 411922 | Raipur | 195 | 195 | 100% | Har Ghar Jal | Not Certified |
| 4 | Hardoi | Shahabad | SHAHPURNAU | 411928 | SHAHPURNAU | 274 | 271 | 99% | Work In Progress | Not Certified |
| 5 | Hardoi | Shahabad | SHAHPURNAU | 411929 | NAU NAGLA | 128 | 125 | 98% | Work In Progress | Not Certified |