Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Vindhya-GAJA (JV) | 20058818 | PURKHIPUR & JOGIBIR DEVDASPUR WATER SUPPLY SCHEME | 491.72 | 271.13 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 27 | Yes | 0 | NA | No | 39136.00 | 39136.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sultanpur | Kurebhar | Purkhipur | 440138 | Purkhipur | 155 | 146 | 94 | Work In Progress | Not Certified |
| 2 | Sultanpur | Kurebhar | Purkhipur | 440139 | Gauhani Dhobibhar | 60 | 60 | 100 | Har Gar Jal | Not Certified |
| 3 | Sultanpur | Kurebhar | Purkhipur | 440140 | Echhuri | 143 | 141 | 99 | Work In Progress | Not Certified |
| 4 | Sultanpur | Kurebhar | Purkhipur | 440141 | Pure Sagar | 54 | 52 | 96 | Work In Progress | Not Certified |
| 5 | Sultanpur | Kurebhar | Jogibir Devdaspur | 440268 | Jogibir Devdas Pur | 98 | 94 | 96 | Work In Progress | Not Certified |
| 6 | Sultanpur | Kurebhar | Jogibir Devdaspur | 440269 | Umar Bhar Jiya Pur | 181 | 175 | 97 | Work In Progress | Not Certified |