Scheme Details
DISTRICT
Moradabad
AGENCY
LC INFRA
SCHEME ID
20058863
SCHEME NAME
Gaura Shahgarh
ESTIMATED COST
267.22
EXPENDITURE
165.43
AUTOMATION STATUS
Not Integrated
SCHEME STATUS
Under Construction
Scheme Physical Progress
Village Coverage
Village Covered
3
T/W Progress
Required
1
Boring Done
1
Air Compressor Done
1
O.P. Unit Done
1
OHT Progress
Required
1
Work Started
1
Work Completed
0
Solar Plant
Required
23
Procured
23
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
9335.00
Meter
Length Laid
8900.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
3 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Bilari | Gaura Shahgarh | 388524 | Gaura Shahgarh | 389 | 378 | 97% | Work In Progress | Not Certified |
| 2 | Moradabad | Bilari | Gaura Shahgarh | 388525 | Saidnagar Urf Nayagaon | 205 | 196 | 96% | Work In Progress | Not Certified |
| 3 | Moradabad | Bilari | Gaura Shahgarh | 677747 | CHOOHARPUR | 1 | 1 | 100% | Har Ghar Jal | Not Certified |