Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Basti | Megha | 20058864 | CHILWANIYA GP wss | 146.48 | 136.32 | view more | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 20 | 20 | Yes | 0 | NA | No | 6941.00 | 10183.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Basti | Chilwaniya | 451122 | Chilwaniya | 162 | 162 | 100 | Har Gar Jal | Not Certified | 
| 2 | Basti | Basti | Chilwaniya | 451123 | Baluwa | 105 | 105 | 100 | Har Gar Jal | Not Certified | 
| 3 | Basti | Basti | Chilwaniya | 451124 | Gangiya Kohal | 57 | 56 | 98 | Work In Progress | Not Certified | 
| 4 | Basti | Basti | Chilwaniya | 451125 | Ram Nagar | 30 | 30 | 100 | Har Gar Jal | Not Certified | 
| 5 | Basti | Basti | Chilwaniya | 680687 | Masjidiya | 48 | 48 | 100 | Har Gar Jal | Not Certified |