Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Sitapur | NCC Ltd. | 20058865 | Gondwa | 629.63 | 194.07 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 6 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 35 | 35 | Yes | 0 | NA | No | 27973.00 | 27800.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Sitapur | Ealliya | Bishunpur | 410187 | Bishunpur | 167 | 153 | 92 | Work In Progress | Not Certified |
| 2 | Sitapur | Ealliya | Bishunpur | 410188 | Nataura | 100 | 90 | 90 | Work In Progress | Not Certified |
| 3 | Sitapur | Ealliya | Bishunpur | 410189 | Sarelli | 149 | 148 | 99 | Work In Progress | Not Certified |
| 4 | Sitapur | Ealliya | Dhoraha | 410196 | Dorha | 300 | 298 | 99 | Work In Progress | Not Certified |
| 5 | Sitapur | Ealliya | Godwa | 410201 | Gondwa | 144 | 130 | 90 | Work In Progress | Not Certified |
| 6 | Sitapur | Ealliya | Godwa | 410202 | Saheb Ganj | 114 | 102 | 89 | Work In Progress | Not Certified |