Track Your Scheme

Know your scheme details, physical progress and current status

Scheme Details
DISTRICT Hardoi
AGENCY NCC Ltd.
SCHEME ID 20058886
SCHEME NAME DULARPUR (GOGP) JJM
ESTIMATED COST 448.56
EXPENDITURE 294.18
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 3
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 30
Procured 30 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 17971.00 Meter
Length Laid 17971.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

3 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Hardoi BEHANDAR DIWARI 413454 DIWARI 409 408 100% Work In Progress Not Certified
2 Hardoi BEHANDAR DULARPUR 413455 DULARPUR 220 219 100% Work In Progress Not Certified
3 Hardoi BEHANDAR DULARPUR 413456 AANT 104 102 98% Work In Progress Not Certified