Scheme Details
DISTRICT
Ayodhya
AGENCY
UNIVERSAL MEP
SCHEME ID
20058900
SCHEME NAME
DHANNIPUR & RAUHNAR UPHAR WSS
ESTIMATED COST
1110.33
EXPENDITURE
575.90
AUTOMATION STATUS
Live
View Live Screen
SCHEME STATUS
Trial Run
Scheme Physical Progress
Village Coverage
Village Covered
4
T/W Progress
Required
2
Boring Done
2
Air Compressor Done
2
O.P. Unit Done
2
OHT Progress
Required
2
Work Started
2
Work Completed
1
Solar Plant
Required
74
Procured
74
KW
Work Status
Yes
Electric
Required
0
Transformer Procured
NA
Work Status
No
Distribution Line
Total Length
37472.00
Meter
Length Laid
37472.00
Meter
Scheme Assigned Villages
Village-wise FHTC, Har Ghar Jal and Certification Status
4 Villages
| Sno. | District | Block | Panchayat | Village ID | Village Name | Households | FHTC | FHTC % | Har Ghar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Sohawal | Dhannipur | 436819 | Budhauli | 100 | 59 | 59% | Work In Progress | Not Certified |
| 2 | Ayodhya | Sohawal | Dhannipur | 436820 | Dhannipur | 209 | 160 | 77% | Work In Progress | Not Certified |
| 3 | Ayodhya | Sohawal | Raunahi Uprehar | 436821 | Majhan Raunahi | 3 | 1 | 33% | Work In Progress | Not Certified |
| 4 | Ayodhya | Sohawal | Raunahi Uprehar | 436822 | Raunahi Uperhar | 1450 | 1383 | 95% | Work In Progress | Not Certified |