Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Basti | VSA | 20058901 | NATAUWA, CHAPILAN GP wss | 436.01 | 233.29 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 8 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 30 | 30 | Yes | 0 | NA | No | 22230.00 | 20214.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Basti | Vikramjot | Chapilanw | 449965 | Chapilanw | 164 | 163 | 99 | Work In Progress | Not Certified |
| 2 | Basti | Vikramjot | Chapilanw | 449966 | Hiyarupur | 118 | 98 | 83 | Work In Progress | Not Certified |
| 3 | Basti | Vikramjot | Chapilanw | 449967 | Badolia | 53 | 46 | 87 | Work In Progress | Not Certified |
| 4 | Basti | Vikramjot | Natauwa | 449968 | Natauwa | 118 | 96 | 81 | Work In Progress | Not Certified |
| 5 | Basti | Vikramjot | Natauwa | 449969 | Paberwa | 51 | 38 | 75 | Work In Progress | Not Certified |
| 6 | Basti | Vikramjot | Natauwa | 449970 | Chirihawa | 44 | 42 | 95 | Work In Progress | Not Certified |
| 7 | Basti | Vikramjot | Natauwa | 449971 | Pure Sukhram | 41 | 32 | 78 | Work In Progress | Not Certified |
| 8 | Basti | Vikramjot | Natauwa | 449972 | Sarsanda | 86 | 67 | 78 | Work In Progress | Not Certified |