Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | GA INFRA - BABA (JV) | 20058915 | FALUDA RAHMATPUR WATER SUPPLY SCHEME | 195.91 | 120.16 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 3 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 16 | 16 | Yes | 0 | NA | No | 7407.00 | 12295.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Saharanpur | Nagal | Falauda | 384464 | Falauada | 219 | 219 | 100 | Har Gar Jal | Certified |
| 2 | Saharanpur | Nagal | Falauda | 384465 | Rahmatpur | 119 | 119 | 100 | Har Gar Jal | Certified |
| 3 | Saharanpur | Nagal | Falauda | 384466 | Akbarpur Urf Bharatput | 36 | 36 | 100 | Har Gar Jal | Certified |