Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status | 
|---|---|---|---|---|---|---|---|
| 1 | Moradabad | NKG-PRIMUS (JV) | 20058985 | RAIBHOOR AND SHERPUR GRAM PANCHAYAT WATER SUPPLY SCHEME | 471.45 | 156.63 | Not Integrated | 
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 4 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 30 | 30 | NA | 0 | NA | No | 19183.00 | 19000.00 | 
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified | 
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Moradabad | Thakurdwara | Sherpur Patti (m.s.t.) | 387742 | Sherpur Patti (m.s.t.) | 392 | 132 | 34 | Work In Progress | Not Certified | 
| 2 | Moradabad | Thakurdwara | Sherpur Patti (m.s.t.) | 387743 | Barhapura(m.s.t.) | 151 | 2 | 1 | Work In Progress | Not Certified | 
| 3 | Moradabad | Thakurdwara | Raibhoor | 387744 | Raibhoor | 341 | 224 | 66 | Work In Progress | Not Certified | 
| 4 | Moradabad | Thakurdwara | Sherpur Patti (m.s.t.) | 681419 | Sherpur Patti Aantmali(M.S.T) | 5 | 2 | 40 | Work In Progress | Not Certified |