Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | UNIVERSAL MEP | 20059060 | HAZIPUR BARSANDI & RAHIMPUR BADAULI WSS | 1132.03 | 557.07 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 2 | 2 | 2 | 2 | 2 | 2 | 1 | 0 | 60 | 60 | Yes | 0 | NA | No | 47473.00 | 47473.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Ayodhya | Sohawal | Hajipur Barsandi | 436776 | Hajipur Barsandi Uparhar | 1370 | 1278 | 93 | Work In Progress | Not Certified |
| 2 | Ayodhya | Sohawal | Rahim Pur Badauli | 436787 | Rahim Pur Baduli | 267 | 267 | 100 | Har Gar Jal | Not Certified |