Scheme Details
| S.No. | District Name | Agency Name | Scheme Id | Scheme Name | Estimated Cost | Expenditure | Automation Integration Status |
|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Vindhya-GAJA (JV) | 20059186 | FAREEDABAD WATER SUPPLY SCHEME | 349.60 | 240.67 | Not Integrated |
Scheme Physical Progress
| Village Covered | T/W | OHT | Solar Plant | Electric | Distribution (Line Laying in meter.) | ||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Required | Boring Done | Air Compressor done | O. P. Unit done | Required | Work Started | Work Completed | Required | Procured (KW) | Work status | Required | Transformer Procured | Work status | Total Length | Length Laid | |
| 5 | 1 | 1 | 1 | 1 | 1 | 1 | 0 | 27 | 31 | Yes | 0 | NA | No | 15742.00 | 13169.00 |
Scheme Assigned Villages
| Sno. | District Name | Bolck | Panchayat | Village ID | Village Name | House Holds | FHTC | FHTC % | Har Gar Jal | Certified |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Bijnor | Netaur | Fareedabad | 386900 | Fareedabad | 275 | 275 | 100 | Har Gar Jal | Not Certified |
| 2 | Bijnor | Netaur | Farid Nagar | 386901 | Kokapur | 60 | 47 | 78 | Work In Progress | Not Certified |
| 3 | Bijnor | Netaur | Farid Nagar | 386902 | Meharpur | 48 | 1 | 2 | Work In Progress | Not Certified |
| 4 | Bijnor | Netaur | Farid Nagar | 386903 | Ishakpur | 32 | 4 | 12 | Work In Progress | Not Certified |
| 5 | Bijnor | Netaur | Farid Nagar | 386904 | Farid Nagar | 72 | 72 | 100 | Har Gar Jal | Not Certified |