Scheme Details
DISTRICT Prayagraj
AGENCY Larsen & Toubro Ltd
SCHEME ID 20059222
SCHEME NAME Saraidina and tejopur Multi Village Water Supply Scheme
ESTIMATED COST 537.91
EXPENDITURE 199.92
AUTOMATION STATUS Not Integrated
SCHEME STATUS Under Construction
Scheme Physical Progress
Village Coverage
Village Covered 6
T/W Progress
Required 1
Boring Done 1
Air Compressor Done 1
O.P. Unit Done 1
OHT Progress
Required 1
Work Started 1
Work Completed 0
Solar Plant
Required 49
Procured 49 KW
Work Status Yes
Electric
Required 0
Transformer Procured NA
Work Status No
Distribution Line
Total Length 37647.00 Meter
Length Laid 37600.00 Meter

Scheme Assigned Villages

Village-wise FHTC, Har Ghar Jal and Certification Status

6 Villages
Sno. District Block Panchayat Village ID Village Name Households FHTC FHTC % Har Ghar Jal Certified
1 Prayagraj Mau Aima Tejopur 431918 Tejopur 160 128 80% Work In Progress Not Certified
2 Prayagraj Mau Aima Tejopur 431919 Jagdishpur Medi 100 88 88% Work In Progress Not Certified
3 Prayagraj Mau Aima Tejopur 431920 Saidaha 74 61 82% Work In Progress Not Certified
4 Prayagraj Mau Aima Tejopur 431921 Ramaipur 139 133 96% Work In Progress Not Certified
5 Prayagraj Mau Aima Tejopur 431922 Raghunathpur Herduwa 93 83 89% Work In Progress Not Certified
6 Prayagraj Mau Aima Saraidina 431968 Saraidina 295 280 95% Work In Progress Not Certified